Engineering

Engineering hours, project management, lead times, and packing specifications.

Parameters
Set global defaults; individual row values can be overridden in the table below.
Spec Level: None
#DescriptionApplicableBase HrsNo. OffRev HrsRev No. OffGrand TotalSite
1Review of SpecificationsBoth0WORKSOP
3QOC Technical Data Sheet (inc SAP BOM)Closure17.5WORKSOP
4SPI Technical Data Sheet (inc SAP BOM)Signaller0WORKSOP
5Termination DrawingClosure1WORKSOP
6QOC GA Drawing & Parts list (choose number of designs that follow this)Closure3WORKSOP
7QOC GA Drawing & Parts list (choose number of designs that follow this)Closure35WORKSOP
8SPI GA Drawing & Parts listSignaller0WORKSOP
9Job Specific NameplateClosure2WORKSOP
10QOC Material Data Sheet (Door) No SpecsClosure1WORKSOP
11SPI Material Data Sheet Signaller No SpecsSignaller0WORKSOP
12QOC Material Data Sheet (Neck) No SpecsClosure1WORKSOP
13Material Data Sheet (Locking Band) New SizeClosure1WORKSOP
14Material Data Sheet (Other)Closure3.5WORKSOP
15Material Data Sheet (Interlock)Closure1WORKSOP
16Weld Overlay Drawings inc layoutClosure10.5WORKSOP
17Detailed Drawings (Modification)Both7WORKSOP
18Detailed Drawings (New Design) (Needs to match Row 7 quantity)Closure35WORKSOP
19FEA Calculations Non code stampedClosure14BANGALORE
20FEA Calculations code stamped (+CE Docs)Closure14BANGALORE
21MAP est by FEA for band and reportClosure0BANGALORE
22Hydro test est by FEA and reportClosure2.5BANGALORE
23Standard FV estimate by calc and reportClosure0BANGALORE
24Integral flange (3D) geometry) calc and reportClosure4BANGALORE
Worksop Total118.5 hrs
Bangalore Total34.5 hrs
Grand Total153 hrs
Total Cost£5,933.49
Worksop Labour Rate: £45/hrBangalore Labour Rate: £17.42/hr